Update 06/05/2026 - SP Energy have removed their schedule from their website whilst they update it. TBH SP Energy had gone off-piste from their own plans.
The One Network site has been 'corrected' and appears to show current works (within normal variance).
Planned work showed below as at 04/04/2026 & did not seem to have change on the subsequent updates to the SP Energy Website - clearly dates may change as the schedule progresses. Sandy Lane has been delayed so that it does not progress in parallel to Rushgreen Road (which was an act of planning madness or incompetence).
All work is planned by SP Energy, using the Contractor Opus Energy:
- Email: lymmreinforcement@spenquiries.co.uk
- Phone (Mon-Fri, 9am-5pm): 0800 188 4481
"We currently have two teams working simultaneously on the project in different areas of Lymm. The work is being completed in stages with the aim of keeping disruption to a minimum. We have an on-site manager who will be in the area for the duration of the project during scheduled hours."
The chart below has been put together from the SP Energy dates (before they pulled them!) here: www.spenergynetworks.co.uk/lymm & is 'correct' as at 04/04/2026. The hashed column is LHS Easter Holidays. As above, this is really for information (showing what is still required).
